30 Humariri Street, Point Chevalier
Year completed
2024
Location
Auckland
Project duration
9 months
No. of Homes
6
Project Scope
6
Competency
Multi-unit Homes
Awards
No items found.
Client
Collaborations
About
Typologies:
1x 4-bedroom standalone
1x 3-bedroom standalone
2x 2-bedroom duplex
Homestar rating: 6
Delivery:
9 months from building consent to council final inspection
16 weeks for house construction (from slab up)
Achieved by use of hybrid offsite manufacturing for simplified, fast onsite installations
and fast, concurrent builds
Highlights:
Challenging compact site with significant excavation and site retaining
Split level frames and lower roofs
No items found.