5-7 Hazards Road, Weymouth
Location
Auckland
Competency
Multi-unit Homes
Project brief
Multi-unit homes delivered through design-and-build.
10 months from building consent to council final inspection. 18.5 weeks for house construction from slab up, achieved through hybrid offsite manufacturing and presheathed balloon frame construction — finished 10 weeks ahead of standard build time. High performer building products including LVL, mammoth insulation and maglock.
Residential DevelopmentsMulti-unit HomesAuckland