Bader Ventura, Māngere
Typologies:
1x 4-bedroom duplex
6x 2-bedroom duplex
12x 3-bedroom terrace
Homestar rating: 8
Delivery:
26 months from site possession to handover
11 months from first precast panel to finished buildings
Impacted by delays in processing building consent for Passive Haus specification
and significant ground remediations
Highlights:
Australasia’s first government funded PassiveHaus certified project
Multi award-winning project
Non-vibration stone column ground remediation used for the first time in Auckland
Precast foundation innovation utilised (we understand this is the first time in
New Zealand). This reduced the construction programme by 10 weeks
High-quality finish
Pre-finished precast balconies utilised, resulting in cost and time reduction
with higher quality